PROJECT
TYPE |
LOCATION |
DESCRIPTION |
Low
Clearance
Mud
Rotary
Drilling |
Lafeyette,
Indiana |
H.A.D., Inc. was contracted to drill and install monitoring wells
inside a building with ceiling clearance ranging from 10 foot
6 inches to 14 foot. Holes ranged in size and depth from 2 inches
to 4 inches from 50 to 150 foot. The job was proposed and started
utilizing hollow stem augers. Augers were advanced to 120 feet
deep, but crews were unable to install a well due to heaving
material in the augers. The hollow stem auger plan was restructured
and drilling was completed by mud rotary methods. Crews had to
endure long house inside working in tight quarters with exceptionally
limited overhead clearance. Most tools had to be brought into
the building by hand. Crews had to adhere to strict health and
safety guidelines and decontamination practices.
|
Monitoring
Well
Installation |
Painesville,
Ohio |
H.A.D., Inc. Performed services at an considerably high profile site
in Northeast, Ohio. An excess of 200 borings were completed
most being converted into monitoring wells. Access difficulties
ranged from mostly wooded areas to wet muddy fields,
to an extremely unstable lime lake. Both hollow stem
augers and probe Geoprobe methods were utilized. All
borings not converted to a well had to be tremmie grouted.
Equipment had to be deconed and all wastes contained.
Drilling had it difficulties ranging from extremely soft
lime substances to drilling in the footprint of a large
manufacturing facility. Concrete, rebar, piping, wood,
scrap steel, train tracks, etc. Were all encountered.
Site security and safety were paramount and all monitored
very closely by the EPA and all parties involved.
|
Low
Clearance Drilling/Monitoring Well Installation |
Bradford,
PA |
H.A.D., Inc. Performed hollow stem augering and direct push services
at an oil refinery located in Bradford, Pennsylvania.
Services ranged from drilling in densely wooded
terrain to drilling in a large tank farm. Many
locations had to be accessed by lifting our drill
rig 60 to 100 feet high and lowering the drill
in-between one million gallon storage tanks. Crews
received specific refinery safety/fire training
to work on site. Crews endured severe temperatures
while working in fire protective suits. Strict
decon procedures were followed. Extreme care was
taken hand clearing each hole to assure no product
or utility lines were hit. During the course of
a five year period HAD was the only drilling company
continuously contacted for this work due to our
professionalism, safety record, and on time delivery
of services. Holes ranged in depth and size from
2" - 6" and 10 feet to 50 feet.
|
Rotosonic
Pipe Retrieval |
Long
Island,
New York |
We were contracted to retrieve quite a length of rotosonic pipe that
another driller had lost in the
hole. Our Barber DR24 drill rig was able
to retrieve 480 feet of sonic drill pipe and save the job! Not only that,
but we completed the job the first driller started by setting a 480-foot
monitoring well with an eleven-foot section of well screen. Click
here for photo documentation of this project.
|
Soil
Vapor
Well Extraction |
Streator,
Illinois |
We were contracted to mobilize to Illinois to drill and install 21 soil
vapor extraction (SVE) wells to depths of 15 to 20 feet below
ground surface. H.A.D. field personnel installed specific
screen lengths and slotted sizes at desired intervals depending
upon what our client encountered at each location. Upon completion,
wells were developed until water quality was satisfactory
to our client. This project was completed in 6 days including
travel time!
|
Soil & Water
Sampling |
Ohio |
We mobilized a two man crew and a GeoProbe® 5400 to
a residential area to retrieve water and soil samples. Crews also set
1-inch PVC monitoring wells. Operators worked under strict decontamination
procedures. Level C equipment was on site in case conditions worsened.
Due to the sensitivity of this location, work had to be performed during
specific hours.
|
Oxygen
Release
Compound
Injection |
Northeastern
Ohio
& West Virginia |
H.A.D., Inc. was contracted by SECOR International, on behalf of a mid-sized
petroleum distributor, to inject oxygen release compound
(ORC) into numerous borings to various depths. This services
was performed at various locations throughout northeastern
Ohio and West Virginia.
|
Monitoring
Well Installation |
Wright
Patterson
Air Force Base -
Dayton, Ohio |
Completed 2-inch monitoring wells to 30 feet below grade in difficult
heaving sand conditions. All field personnel obtained a security
clearance. All well locations were in densely vegetated areas
which made access difficult. We observed strict rules and
regulations in addition to health and safety procedures.
Decontamination was performed upon arrival, between each
bore hole and prior to de-mobilization from the site.
|
Monitoring
Well Installation |
Northeastern
Ohio |
Crews drilled and installed more than 20 two-inch diameter monitoring
wells at a steel foundry. Drilling conditions included a
difficult to penetrate slag and steel fill. Crews completed
monitoring wells with flush-mounts and pro-casings each surrounded
by 3-4 guard posts. To accommodate our customer's schedule,
crews worked throughout the week, including Saturdays. In
some instances the customer had both our CME-75 and
our CME-85 working side by side.
|
Monitoring
Well Installation |
Wayne
County,
Ohio |
Our CME-85 mobilized to this location and
installed 6-inch casing. Immediately afterwards, our Ingersoll-Rand
TH60 was mobilized to rock core. Crews averaged 100 feet per day
of coring, providing the customer with a 3-inch diameter, 20-foot-long
core. Crews cored at an average rate of 2 feet per minute.
|
Monitoring
Well Installation
& GeoProbe® |
Northern
Pennsylvania |
Our EarthProbe 200® was mobilized to
an oil refinery to install approximately 7- soil borings to 12 feet deep
each. Samples were collected from various locations, including the dike
walls surround aboveground oil storage tanks.
After our EarthProbe 200® work was completed, we mobilized a CME-85 and
a skid-mounted CME-LC60. A 3-man drilling
crew installed over 500 feet of four-inch diameter wells. Crews worked
under strict decontamination procedures. A crane operator was on stand-by
to lower the CME-LC60 into several tight access areas.
|
Monitoring
Well Installation, Exploratory
Drilling, & Water Well Abandonment |
Akron,
Ohio
|
In the spring of 1999 H.A.D., Inc. mobilized a CME-85 to
drill and install a deep monitoring well in heaving sands, and a track-mounted CME-LC60 to
install various monitoring wells in the woods and other locations. Crews
were required to mobilize through a creek to access one particular drilling
location. Our REICHDrill T-690 was
mobilized to drill exploratory borings approximately 460 feet in overburden
on fluid, and our Bucyrus Erie 22-W Cable
Tool Drill Rig was used to abandon a residential water well. H.A.D.,
Inc. had several pieces of equipment on site simultaneously to complete
the work within the customer's time frame for the project, but Ohio's
spring weather was not cooperative.
|
Exploratory
Drilling |
Eastern
Ohio |
H.A.D., Inc. mobilized our CME-85 to
this location for LaFarge Corporation, the world leader in aggregate
products. Crews were drilling to 70 feet with the CME-85 continuous sampling
tube system, providing the customer comprehensive samples with which
to estimate aggregate reserves. We cased the overburden with our Ingersoll-Rand
TH60 and cored limestone to determine the thickness and
quality of the formation.
|
Deep
Well
Installation |
Garfield
Heights,
Ohio |
A CME-75® drill rig
accompanied by a 3-man drill crew was mobilized to the site to drill
and install a monitoring well to 285 feet in depth. The soil was sampled
at five foot intervals and rock cores were taken to 285 feet. Specific
permits were required and obtained by H.A.D., Inc. due to this drilling
location. The drilling location was restored to its original condition
by our crews.
|
Water
Well
Installation |
Northeastern
Ohio |
We were contracted to drill and install a water well at an active gasoline
station. The well was completed to a total depth of 147 feet
below ground surface. Crews worked on this fast track project
to comply with the client's need for water in addition to
the EPA's requirements.
|
Municipal
Water Wells |
Delaware,
Ohio |
Our drilling crews worked in conjunction with Ohio Drilling Company in
Delaware, Ohio, drilling 3 high-volume, large diameter water
supply wells for the City of Delaware. The wells were 16
inches in diameter and 250 feet deep. Each well test-pumped
at 1,500 gallons per minute in a dolomite formation with
little draw down. This long-term project was completed successfully
after months of drilling.
|
Emergency
Water Well
Servicing |
Atwater,
Ohio |
H.A.D., Inc. was contacted 48 hours before the school year was to begin.
Crews worked around the clock to restore Waterloo Primary
School's water supply. Field personnel worked in conjunction
with the EPA and Waterloo School District.
|
Hazardou
Chemical /
Level B PPE |
Northwestern
Pennsylvania
|
H.A.D., Inc. was contracted to drill at an abandoned dump site in northwestern
Pennsylvania. Because the contaminants were unknown and there
were reports of former on-site workers being exposed to hazardous
chemicals, H.A.D., Inc. was required to perform all drilling-related
tasks in Level B PPE. Hollow stem augering, sampling, well
installation, development, and decontamination were completed
on-site in Level B PPE and incident-free. The scope of work
was completed ahead of schedule despite the warm temperatures
that placed crews under a great deal of stress. As an added
measure of safety, H.A.D., Inc.'s senior driller and Health
and Safety Officer were on the site. All customer information
remains confidential.
|